Current Projects

Traffic Pattern Change

Due to an ongoing pattern of close calls & resident concerns, Farnsleigh Rd. between Somerset Dr. and Belvoir Blvd. is now one-way heading southwest.

Cuyahoga County Department of Public Works: 

Cedar Road Resurfacing Project

All of the following dates are based upon favorable weather conditions.

Start Date - June 9 & 10

On Sunday night June 9th the Phase 2 Traffic Zone (Legacy Village to 1-271) will be set up. By Monday morning June 10th the phase 2 zone will be restricted to one lane in each direction. The Contractor will be working on the Beachwood side first (south side of the road) and the traffic will be maintained on the North side of the road, in Lyndhurst.

On Monday night June 10th the contractor will close Richmond Road and remove the asphalt in this entire intersection via grinding. The intersection closing will only be for a few hours. Once they finish the intersection, they will continue on the south side of the road removing asphalt and the intersection will be open. The exact timing of the closure is being discussed with the contractor, the County and the Police. 

Start Date - June 5 & 6


Update: The overnight roadwork scheduled for June 5 & 6 has been postponed to June 6 & 7 due to unfavorable weather on June 5. 
Asphalt resurfacing on Cedar Road from Green Road to Legacy Village Drive will take place at night on June 5 and June 6. Night work will begin at approximately 8:00 PM and will be completed by 6:00 AM. Cedar Road will be open to two-way traffic at all times. Half of the road will be paved on the night of June 5 and the other half on the night of June 6.

Pavement markings, loop detectors and clean-up of the Phase 1 zone will occur after the paving is completed and the roadway will be opened to traffic sometime over the weekend of June 8 and 9.

Start Date - May 7th

The Perk Company will begin maintaining traffic on the NORTH side of Cedar Road one lane in each direction from south Green to Richmond Road while road reconstruction is performed on the south side of Cedar Road.

Start Date - March 28th

Perk Co. will begin the resurfacing of Cedar Road from Green Road to 271, east and westbound lanes

Project will start westbound, from Legacy Village to Green Road in South Euclid and Lyndhurst.

Traffic on Cedar road will be down to two lanes and alternate routes should be planned as this project will continue for the next seven months.

Dominion East Ohio

Start Date - April 22

Wartko Construction will begin gas line replacement on Fairmount Boulevard. Brentwood Road, Fernwood Drive, Elmhurst Drive, and Ranch Road.  Roads will remain open during construction but limited to one lane in each direction.  This project is expected to be completed by the end of July, weather permitting.

Future Projects

Halburton Road Improvements
REVISED START DATE - June 17

Tri-Mor Corporation will be installing new road, aprons and curbs on Halburton between Brandon and Letchworh.  During construction, traffic on Halburton will be west-bound only. This project is expected to be completed within 80 days, weather permitting.


Barkwood Dog Park

Our Public Works Department has made progress on the Barkwood dog park site.  Water and electric utilities have been installed.  Barkwood is located at Beachwood City Park East on the east side of Richmond Road between Shaker Boulevard eastbound and westbound.

As you can see, it's a pretty spot. (It will look even better with your pretty Spot.)

Soon to be unleashed, Barkwood, Summer 2019
Barkwood Site 4
Barkwood Site 5
Barkwood Site 2
Barkwood Site 3
Barkwood Site 1
Back Hoe Putting in a Gravel Walkway